Pattern Imprinted Concrete Installation

The installation process is the interesting part of the job.

For a closer look at how we create this beautiful work see below for our step by step explanation.

Day One, Let the digging commence:

Our first task upon arrival on site is to fully excavate the site. This will either be a manual operation or heavy plant and machinery may be used, depending on the size of the task in hand.

The site is then dug out to a depth 4-8″ allowing for 4″ concrete and the necessary sub-base.

Finally the site is compacted and the shuttering put in place to determine the final shape of the area. We are now ready for Day 2.

Day Two, The pouring:

At this stage the project really begins to take shape.

The wet concrete is delivered from a ready-mix concrete lorry into wheel barrows or a dumper. It is then layed and levelled ensuring that all future rainwater will fall off leaving no puddles.

The surface is then completely smoothed off and a dry colour hardener (base colour) scattered over the top. This colour is then floated in using trowels.

The secondary release-agent colour (chalk-based) is then applied. The textured and patterning mats are then stamped in all over the area. (the chalk prevents sticking). The main stage is now over.

Day Three, The Finish:

This stage will be done over 1 or 2 days depending on the time of year and weather conditions.

Firstly, the crack control joints are cut in to a depth of an inch approx.

The site is then completely pressure-washed as are the surroundings.

The crack control joints are then filled with mastic.

When completely dry the area is sealed, which immediately enhances the look and protects it for years to come.

Driveways Gallery

Paths & Walkways

Patios Gallery

Bespoke Gallery

Contact Form

11 + 9 =

Belle Green Driveways Ltd

Unit 14A Belle Green Ind Estate
Belle Green Lane
Wigan
Greater Manchester
WN2 2EP

T: 01942 493343

M: 07949 487165

info@bellegreendriveways.co.uk